Construction Update

FEBRUARY 2025

IMG_20250225_112301.jpg
IMG_20250225_104218.jpg

Tower 1 Structure work at 39th floor in progress

Tower 2 Structure Complete, Finishing in progress

Tower 3 Structure Complete, Finishing in progress

IMG_20250225_104144.jpg

Tower 4 Structure work at 1st floor in progress

IMG_20250218_112629.jpg

Tower 5 Structure work at 36th floor in progress

IMG_20241231_114509_edited.jpg
IMG_20250218_123446.jpg

Tower 6 Structure Complete, Finishing in progress

Tower 7 Structure Complete, Finishing in progress

IMG_20240527_180733.jpg

Tower 8 Structure work at 1st floor in progress

Tower 9 Structure work at Ground floor in progress

IMG_20250225_112219.jpg
IMG_20240527_180157.jpg
IMG_20250218_123241.jpg

Tower 10 Structure work at 1st Basement in progress

RERA REGN NO. - 29 OF 2022